In a statement on the Auditor General’s Report (LKAN) 2/2026, the department said the delay posed a risk to the Physical Handover (PHO) of LCS 1, initially scheduled for Aug 26, 2026, and the revised ...
PETALING JAYA: The littoral combat ship (LCS) project is running behind schedule again with weaknesses found in its implementation.
1monon MSN
LCS project hits fresh snagReport: Vessels face further delays, putting Dec 26 handover at risk
PETALING JAYA: The Littoral Combat Ships (LCS) project has run behind schedule again, as the Auditor-General has found weaknesses in the progress of the vessels.
The LCS project was 7.55% behind schedule across all five ships, while LCS 1 was 13.88%, or 108 days, behind in equipment, construction, trial and commissioning work. The navy’s first littoral combat ...
Two defence analysts say the vessels would still enhance the navy’s capabilities, but one also calls for an RCI to probe the troubled project.